An electrical takeoff is three lists stacked on top of each other: the devices and light fixtures, the distribution equipment that feeds them, and the conduit and wire that connect everything. Each list comes from different sheets, and each one is easy to get wrong in its own way. The order below catches the most mistakes: legend and schedules first, then devices, then gear, then raceway and wire, then the small parts and the questions.

Div 26the specification section for electrical; fire alarm is often Division 28
3layers: devices and fixtures, gear and feeders, conduit and wire
by typeevery fixture counted by its schedule letter, never as one total
x conductorswire length is conduit length times the conductors in it

Step one

Read the legend, the schedules, and the specification first.

The symbol legend says what every mark on the plans means: duplex receptacle, GFCI, quad, floor box, single-pole switch, three-way, dimmer, occupancy sensor, data outlet, and so on. Many legends also note mounting heights. The light fixture schedule lists every fixture type by letter (A, B, C, or F1, F2, F3), with its description, lamp, voltage, and mounting. The one-line diagram and the panel schedules show the gear. Division 26 sets the wiring methods: where EMT is allowed, where MC cable is allowed, minimum wire size, and the box and device standards.

Read all of it before counting. A symbol counted before its legend is read is the most common way an electrical count goes wrong.

Step two

Count devices and fixtures, one sheet at a time.

Work a sheet at a time and keep a count per sheet. Count each device by its symbol and each light fixture by its type letter. Do the lighting plans and the power plans separately, because they are drawn separately. Then turn each count into its parts: a receptacle is the device, the box, the mud ring, and the plate; a fixture is the fixture, its support, and its whip or connection.

Emergency fixtures, exit signs, and the sensors and switches of the lighting controls each have their own symbols. They are easy to lump in with ordinary fixtures and devices, and they are priced very differently.

Step three

Take the gear and feeders from the one-line.

The one-line diagram names the service, the switchboards, panelboards, transformers, and disconnects, and the feeder between each pair: how many sets, how many conductors, what size, and what conduit. Count the gear from the one-line, then check it against the plans. Measure each feeder on the plans from one piece of gear to the next, plus the vertical drops and rises at each end.

The panel schedules list every breaker by pole count and amperage. Counting breakers from the schedules is faster and more accurate than counting circuits on the plans.

Step four

Measure conduit by size, then turn it into wire.

Measure each conduit run by size, with the vertical drops from the ceiling to each device at its mounting height. Branch circuits are often drawn only as a home-run arrow to the panel, so the route is not shown. When it is not, say so and state the method used, such as measuring the path along the walls and corridors to the panel.

Wire comes from the conduit. For each run, the wire length is the conduit length times the number of conductors in it, including the ground, plus a stated allowance at each box for makeup. Keep each wire size separate. Check conduit fill against the code tables for the larger feeders, and remember that the code limits the bends between pull points, which adds pull boxes on long runs.

Step five

Add the small parts, then list the questions.

Last come the parts that make the counts work: supports and hangers, fire stopping at rated walls, labels, and the testing the spec requires. Then write down the exclusions and the questions: routes that were not drawn, fixtures not on the schedule, mounting heights that were not given, and any work that belongs to another division, such as fire alarm or low-voltage controls.

The result is a takeoff the contractor can price and the supplier can quote: devices and fixtures by type, gear by size, conduit and wire by size, each with the sheet it came from. Matchline is a SaaS builder: we build a takeoff-to-quote system for one business at a time and run it under that business’s name. There are no seats and nothing is priced per job. A build fee, then a monthly fee, both in writing before anything starts. A person reviews every job before it is released.

How it runs

What changes when a system does the reading.

  1. 01

    Set up

    Your lines go in as product packs: catalog, rules, the maker’s drawing content, cut sheets, your list price file by version. Your tiers, your quote format, your ERP’s import layout.

  2. 02

    Upload

    Your customer, or your own estimator, drops the drawing set and a bid date on a portal with your logo on it. A receipt goes to both sides.

  3. 03

    Read and review

    The set is read against its schedules and specification. Each count is stored with the page and the region it came from. A person checks every value against its sheet before release.

  4. 04

    Release

    The quote at the right tier, the scope sheet, the submittal, the production files. The price snapshot is locked; later price changes never touch an issued quote.

Questions

Asked about electrical takeoffs.

Should I count circuits from the plans or the panel schedules?

Breakers from the panel schedules, devices from the plans. The schedules are faster and list every breaker; the plans show where each device is.

How do I estimate wire when branch routes are not drawn?

Measure a realistic path along walls and corridors to the panel, state that method, and keep the allowance at each box as its own figure so it can be checked.

Is fire alarm part of the electrical takeoff?

Often not. Fire alarm is usually Division 28 and may be a separate contractor. Check the scope and list it as included or excluded.

What about low-voltage lighting controls?

Count the sensors, switches, and control panels as their own lines, and check whether the control wiring is in the electrical scope or a separate one.

What does a takeoff system change?

Who touches the set. The system we build reads the uploaded set and returns the takeoff in the business’s own products and prices, with the sheet cited per line and a person reviewing before release.

Related

Other pages on this.

Talk to us

Tell us what you sell against a drawing set.

What you sell, how a set reaches you, how it gets priced, and what you want back. From that we scope a build in writing.

info@matchline.studio
Or tell us here. A person reads it and writes back.
The team that reads it is the team that builds it.