A takeoff is a list of what a drawing set calls for, counted and measured so someone can price it, order it, or build it. Every trade counts a different list, but the rules underneath are the same: read the set in order, trust the dimensions over the ruler, count one sheet at a time, keep every count tied to the sheet it came from, and ask instead of guessing. This handbook puts those rules and every trade’s list on one page. It applies by hand, in a PDF tool, or in any software.

8trades on one page: plumbing, duct, electrical, data, sprinkler, panels, seating, and furniture
5rules that apply to every takeoff, whatever the trade
10checks to run before a takeoff is priced
1line per count, with the sheet it came from

Part one

Five rules for every takeoff.

Read the set in order. The cover sheet and the sheet index tell you what is in the set and what is missing. The general notes, the legends, and the schedules tell you what every symbol and tag means. The specification tells you what each item is made of. Only then open the plans. Most takeoff errors start with a plan sheet read before its legend.

Trust the dimensions, not the ruler. A printed set is often half size, a PDF is often scaled to fit, and some details are marked NTS (not to scale). Before measuring anything, check the sheet’s stated scale against a dimension written on the same sheet. If they disagree, the written dimension wins, and the scale is a question.

Count one sheet at a time. Keep a count per sheet, mark what has been counted, and add the sheets up at the end. Enlarged plans repeat what the floor plan shows, so count from one or the other and say which.

Tie every count to its sheet. A number nobody can find on the drawings is a number nobody can check. Every line in a takeoff should say which sheet, and ideally which spot, it came from.

Ask, do not guess. When the plan and the schedule disagree, when a height is missing, or when a symbol is not in the legend, the takeoff lists the question. A takeoff that lists its questions is worth more than one that silently picked an answer.

Part two

Know the set: sheet letters and spec divisions.

Most American drawing sets follow the National CAD Standard, which gives each discipline a letter. The letter on the sheet number tells you whose sheet it is, so you can find every sheet your trade needs before you start. Many trades also need sheets that are not theirs: a plumbing takeoff needs the architectural plans for ceiling heights, and a seating takeoff needs the structural sheets for the risers.

The specification follows MasterFormat, which numbers the work by division. Your trade’s division names the acceptable manufacturers, the materials, and the installation rules that change what you count. Read it, even when the drawings seem to say everything.

Part three

Scale, units, and the lengths things are sold in.

Architectural plans are usually drawn at 1/8 in. = 1 ft (1:96) or 1/4 in. = 1 ft (1:48), with enlarged plans and details at larger scales. Civil and site sheets use engineering scales such as 1 in. = 20 ft or 1 in. = 50 ft. A sheet can carry more than one scale, one per view, so read the scale under each view, not just the one in the title block. Printed half size, a 1/8 in. plan measures at 1/16 in., which is why the dimension check in rule two matters.

Measured lengths become ordered quantities only after rounding to what the material is sold in. Each size rounds up on its own, and waste is its own line at a stated rate, never hidden inside a length.

Trade by trade

Plumbing.

A plumbing takeoff is fixtures with everything that makes each one work, plus pipe by system and size. Start with the fixture schedule: every tag (WC-1, L-1, S-1, FD-1, and so on) and its model, mounting, and connections. Count tags per plan sheet and reconcile the total to the schedule. Then turn each tag into an assembly: a wall-hung water closet is the bowl, the flush valve, the carrier, the seat, the stop and supply, and the gasket and bolts, which is six lines, not one.

Pipe is listed by service (cold water, hot water, hot water return, sanitary, vent, storm, and gas), then by material, then by size, with horizontal runs from the plans and verticals from the risers and floor-to-floor heights. Fittings are counted at every turn, branch, and size change. The full plumbing method is here.

Trade by trade

HVAC and dust-collection duct.

A duct takeoff lists every straight by size and length, every fitting by type and size, and the hangers, dampers, and accessories each run needs. The equipment schedule gives the connection sizes; Division 23 gives the material, the gauge by size, the pressure and seal class, and the hanger spacing. Follow each system from the equipment to the last terminal, starting a new line every time the size changes.

Fabricated rectangular duct is often priced by the pound of metal; round, spiral, and clamp-together duct is priced by the piece and the foot. Count the way the product is priced. The full duct method is here.

Trade by trade

Electrical.

An electrical takeoff has three layers. First, the devices and fixtures: receptacles, switches, sensors, and light fixtures counted by symbol and by type from the legend and the lighting fixture schedule, each with its box, plate, and mounting. Second, the distribution: panels, transformers, disconnects, and feeders from the one-line diagram and the panel schedules. Third, the raceway and wire: conduit by type and size, and wire by size, where the wire length is the run length times the number of conductors, plus the makeup at each end.

Branch-circuit routing is often not drawn, only home runs marked with arrows, so the takeoff states the method used to estimate the routes. Lighting controls, emergency fixtures, and exit signs each have their own symbols and are easy to lump together by mistake. The full electrical method is here.

Trade by trade

Data and communications cabling.

A structured-cabling takeoff starts with the outlets: each symbol on the T sheets has a legend entry that says how many cables it gets and of what type. Count outlets by type, multiply out the cables, and assign each outlet to the telecom room that serves it. Cable length per drop is the horizontal route plus the drop down the wall plus the slack the specification requires at each end.

The cabling standard (TIA-568) limits a horizontal permanent link to 90 meters, or about 295 feet. A drop that measures longer either goes to a different room or is a question for the designer. Cable is bought by the box or reel, so the total footage per cable type rounds up to whole boxes. Then count the rest: jacks, faceplates, patch panels, racks, cable management, and pathway such as J-hooks or tray. The full data cabling method is here.

Trade by trade

Fire sprinkler.

Sprinkler systems are often delegated design: the drawings show the intent and the hazard classes, and the sprinkler contractor lays out and calculates the system. So a takeoff from bid documents is often a budget built from coverage, such as heads per area by hazard class, plus the risers, valves, and fire department connection the drawings do show. Say plainly which it is.

When the layout is drawn, count heads by type (pendent, upright, sidewall, concealed, and dry), pipe by size, and the valves, hangers, and seismic bracing the spec requires. The full sprinkler method is here.

Trade by trade

Architectural metal panels.

A metal panel takeoff is read from the elevations, not the plans. Each elevation is broken into panels at the module the drawings show, and each panel is listed at its dimensioned size, because panels are made to size. Openings for windows and doors are deducted, and the area is checked against the elevation’s overall dimensions.

Then the linear items: trims, flashings, closures, and copings by the foot and by profile, plus corners, sills, and jambs at every opening. Sub-girts, clips, and fasteners follow the system and the spec. Wall sections tell you what the panel attaches to, which changes what else gets counted. The full metal panel method is here.

Trade by trade

Fixed auditorium seating.

A fixed seating takeoff counts chairs row by row. Each row has a length set by the aisles and walls, and the chairs in it come in several widths that are mixed to fill that length. So the count is per row: how many chairs of each width, plus the aisle ends, and whether the row is on a riser or a slope.

Accessible seating is its own count: wheelchair spaces, companion seats beside them, and aisle seats with folding or removable arms, as the code and the drawings require. Row letters and seat numbers, end panels, and any options in the spec (cup holders, tablet arms, and aisle lights) are lines of their own. The full fixed seating method is here.

Trade by trade

Contract furniture.

A furniture takeoff is read from the furniture plans on the I sheets and the furniture schedule or FF&E list. Each tag on the plan points to a product with its options and finishes. Workstations are usually drawn as typicals, so the count is the number of each typical times the parts in it, not the number of desks drawn.

Finishes and options make the difference between a quote and a guess: the fabric grade, the laminate, the base, and the arms all change the price and the part number. The result usually goes into dealer order entry as a SIF file, so every line needs the manufacturer’s part number and options, not just a description. The full furniture method is here.

Part four

Ten checks before a takeoff is priced.

Run these before anything goes to pricing. Each one catches a mistake that is cheap to fix now and expensive after the bid is in.

  1. Every sheet in the index was opened.
  2. The scale was checked against a written dimension on each measured sheet.
  3. Every count was reconciled to its schedule, and each difference is listed.
  4. Enlarged plans and floor plans were not both counted.
  5. Every tag on the plans is in a schedule, or it is listed as unscheduled.
  6. Every length was rounded to sold lengths, per size.
  7. Waste is a separate line at a stated rate.
  8. Every addendum was read and applied.
  9. Exclusions are written down.
  10. Every line names the sheet it came from.

Part five

Glossary.

  • Takeoff: the list of what a drawing set calls for, counted and measured.
  • Quantity takeoff: the counts and measurements.
  • Material takeoff: the quantities turned into orderable products and sizes.
  • Estimate: the takeoff priced, often with labor.
  • Schedule: a table on the drawings listing every tag of a type.
  • Tag: the label that ties a symbol on the plan to a schedule line.
  • Legend: the key to symbols and line types.
  • Typical: a layout drawn once and repeated.
  • Addendum: a change issued during bidding.
  • Basis of design: the product the designer specified, with equals allowed by the spec.
  • Or-equal: an accepted substitute.
  • Delegated design: work the contractor designs, such as sprinklers.
  • NTS: not to scale.
  • SIF: the standard interchange file for furniture order entry.

How it runs

What changes when a system does the reading.

  1. 01

    Set up

    Your lines go in as product packs: catalog, rules, the maker’s drawing content, cut sheets, your list price file by version. Your tiers, your quote format, your ERP’s import layout.

  2. 02

    Upload

    Your customer, or your own estimator, drops the drawing set and a bid date on a portal with your logo on it. A receipt goes to both sides.

  3. 03

    Read and review

    The set is read against its schedules and specification. Each count is stored with the page and the region it came from. A person checks every value against its sheet before release.

  4. 04

    Release

    The quote at the right tier, the scope sheet, the submittal, the production files. The price snapshot is locked; later price changes never touch an issued quote.

Questions

Asked about takeoffs in general.

What is the most common takeoff mistake?

Counting a room twice: once on the floor plan and again on the enlarged plan. The second most common is measuring a sheet that was printed or exported at a different scale than the one written on it.

Should the takeoff match the schedule?

It should be checked against it. When the plan count and the schedule count differ, list both and ask the designer. The schedule is what the job calls for; the plan is what is drawn.

How much waste should I add?

The rate your business uses for that material, as its own line. Waste hidden inside a length cannot be checked, and it tends to get added twice.

Do I need the specification if the drawings have schedules?

Yes. The schedule names the product; the specification names the accepted equals, the materials by service, and the rules that add items the drawings never show.

What makes a takeoff trustworthy?

That anyone can check it. Every line says what it is, how many, and which sheet it came from, and every open question is written down.

What does a takeoff system change?

Who touches the set. The system we build reads the uploaded set and returns the takeoff in the business’s own products and prices, with the sheet cited per line and a person reviewing before release.

Related

Other pages on this.

Talk to us

Tell us what you sell against a drawing set.

What you sell, how a set reaches you, how it gets priced, and what you want back. From that we scope a build in writing.

info@matchline.studio
Or tell us here. A person reads it and writes back.
The team that reads it is the team that builds it.