Olympus Painting: one handwritten digit, $708,000
West Virginia DOH v. Olympus Painting Contractors, Inc., W. Va. Intermediate Court of Appeals, 2025
What happened. On a bridge repainting bid, 177 feet of expansion joint was priced at $9,340 a foot. A clerical employee read the handwritten 9 as a 5 and entered $5,340. The bid came in at $5.6 million, about $1.6 million below the next bidder, with a $280,315.82 bid bond at stake.
Outcome. The trial court let the contractor out and returned the bond. On appeal, most of that was affirmed, but the question of whether an error happened at all was sent back for another look.
For a takeoff. A handwritten unit price retyped by someone else is a single point of failure. Check every unit price times quantity against the estimator’s own extension.
Kemper: a $301,769 line left off the summary
M. F. Kemper Construction Co. v. City of Los Angeles, Supreme Court of California, 1951
What happened. Estimators working until 2 a.m. on bid day priced an item at $301,769 on a work sheet, then left it off the final summary sheet. The bid was $780,305; the other bids started at $1,049,592.
Outcome. The city accepted the bid, gave the job to the next bidder, and demanded the bid bond. The court allowed the contractor to rescind and discharged the bond.
For a takeoff. Reconcile the summary against every detail sheet. Fatigue is when lines get dropped.
Kastorff: the plumbing that was never in the bid
Elsinore Union Elementary School District v. Kastorff, Supreme Court of California, 1960
What happened. A $9,285 plumbing sub-bid was replaced at the last minute by a $6,500 one. Believing the first was already in his total, the contractor took $3,000 off. In fact, no plumbing was in the bid at all. The bid was $89,994, $11,306 below the next.
Outcome. The district re-let the job at $102,900 and sued for the difference. The court reversed the judgment for the district: an honest clerical error, promptly reported, could be rescinded.
For a takeoff. A last-minute swap has to be traced into the total, not patched with a lump sum at the bottom.
Taylor & Son: $100,000 from a digit not carried
James T. Taylor & Son, Inc. v. Arlington Independent School District, Supreme Court of Texas, 1960
What happened. Adding the profit margin to the estimate total, the contractor failed to carry a digit, and the bid of $534,175 came out $100,000 low. It was the lowest of nine. The district went after $36,278 on the bid bond.
Outcome. The court held that ordinary negligence does not bar relief, but sent the case back for trial on whether a mistake was actually made.
For a takeoff. Markups and roll-ups are arithmetic too. They need the same independent check as the takeoff lines.
Smith & Lowe: $20,798 of simple addition
Smith & Lowe Construction Co. v. Herrera, Supreme Court of New Mexico, 1968
What happened. A county jail bid of $590,630 carried a $20,798 error in simple addition. The next bid was $43,370 higher.
Outcome. The county awarded at the mistaken price anyway, then went to the second bidder. The contractor was allowed to rescind without losing its bid bond.
For a takeoff. A footing check on the bid summary catches this before it is submitted.
Mountain Home: $15 instead of $115 a square
American Insurance Co. v. Mountain Home School District No. 9, Supreme Court of Arkansas, 1989
What happened. Roofing on a junior high school was quoted at $15.00 a square instead of $115.00, across 804 squares. One dropped digit.
Outcome. The trial court entered judgment against the contractor and its surety for $85,728 plus interest, a penalty, and fees. The supreme court reversed and sent it back to decide rescission.
For a takeoff. A dropped leading digit is invisible in a total. Compare each unit rate to the range you normally see.
Ronlee: a $525 culvert entered at $5.25
Department of Transportation v. Ronlee, Inc., Florida Third District Court of Appeal, 1987
What happened. A phone quote of $525 per concrete culvert was written down as $5.25 each. On a $15.8 million highway bid, the error was $317,463.
Outcome. The contractor signed, started work, and then asked for the money. The trial court awarded it; the appeals court reversed. Once the contractor built at the bid price, the price stood.
For a takeoff. Check every phone or verbal quote against a written confirmation before it goes in. Once you build, you own the error.
Construction Technology Group: a spreadsheet off by one line
Construction Technology Group, Inc., GAO B-283857, 2000
What happened. On an Air Force dining facility, a spreadsheet formula pulled prices from line 8 instead of line 7, leaving three line items out of the totals. The low bid was $4,242,500.
Outcome. The agency allowed a $330,500 upward correction, and GAO denied the protest against it.
For a takeoff. Spreadsheet sum ranges need an independent cross-check, every time.
Roy Anderson: a $3.7 million electrical item outside the sum
Roy Anderson Corp., GAO B-292555, 2003
What happened. On an Army barracks bid, the subtotal formula summed rows 16 through 158 instead of 159, leaving out a $3,702,025 electrical item. With markups, the bid of $35,574,639.50 was understated by $3,923,700.
Outcome. The agency allowed the correction to $39,498,340, and GAO denied the protest.
For a takeoff. An off-by-one range silently drops the last trade. Check that the subtotal covers every line.
Herman Construction: a $500,000 plug for a $1.5 million quote
Herman Construction Group, Inc., GAO B-415480, 2018
What happened. A bidder on a VA emergency department carried a $500,000 placeholder for drywall instead of the $1,498,770 quote it had received the day before. Its low bid was $6,635,332.
Outcome. The VA allowed a correction to $7,771,658. GAO sustained the protest: nothing in the bidder’s records tied the worksheet to the quote, so the mistake could not be proven.
For a takeoff. An unlabeled placeholder that looks like a real number cannot be fixed later. Flag every plug where anyone can see it.
Emma Corp.: a $786,000 trade entered at $2
Emma Corp. v. Inglewood Unified School District, California Court of Appeal, 2004
What happened. An estimator meant to type a 1 on one line and typed it on two. A $786,000 plumbing and site utilities sub-bid went in at $2.00. The bid was $8,150,000 with an $815,000 bid bond.
Outcome. The withdrawal letter missed the statute’s requirements, but the district knowingly stayed silent about that, so it could not keep the bond. The contractor won.
For a takeoff. One keystroke on the wrong line can delete a whole trade. Compare each trade’s carried total to its quote.